During final closeout activities for a project, the project manager identifies that project charter contains an original project scope that is less costly than the final project scope. What should the project manager do with this information? 在一个项目的最终收尾活动期间,项目经理发现项目章程包含的原始项目范围比最终项目范围的成本低,项目经理应如何处理这项信息? ◑A. Document the original and final scopes in the project report.在项目报告中记录原始和最终范围。 ◑B.Change the project charter to reflect all the changes made post-creation of this document.更改项目章程以反映本文件创建后所做的所有变更。 ◑C.Verify whether the project management plan has been updated.核实项目管理计划是否已更新。 ◑D.Review the change request and, if it does not contain the necessary information, update is.审查变更请求,且如果没有包含必要的信息,则更新该变更请求。