A key resource requirement for a project subcontractor is technical expert on a manufacturing process. During the early stages of the project, it becomes clear that the subcontractor’s staff has inadequate expertise to meet the quality standards. What should the project manager do? 项目分包商的一位关键资源需求是一个制定过程的技术专家。在项目的早期阶段,很明显分包商的员工缺乏足够的专业知识来满足质量标准。项目经理应该怎么做? ◑A.Update the risk register.更新风险登记册。 ◑B.Appoint a subject matter expert (SME) to the project team为项目团队成员指定一名主题专家(SME)。 ◑C.Perform a quality audit of the subcontractor.对分包商执行质量审计。 ◑D.Review the contract for any relevant penalty clause.审查合同中的任何相关罚款条款