Advances in technology create an organizational need to improve a product line’s specifications to stay ahead of competitors. However, the budget for this financial year is already under significant strain, leaving very little funding available for new project.What should the project manager do?
技术进步创造了一项组织需求,需要改善一个产品线的规范,从而保持领先于竞争对手。但是本财政年度的预算已经处于巨大压力之下,新项目的可用资金很少,项目经理应该怎么做?
◑A.Wait for the new financial year to make any changes in product advancements等到新的财政年度再对产品改进做出任何变更
◑B.Perform a cost-benefit analysis of the business case to illustrate the benefits of implementing the project对商业论证执行成本效益分析,以说明实施项目的好处
◑C.Calculate the ROI to decide if it makes sense to proceed with the project计算ROI以确定继续执行该项目项是否有意义
◑D.Calculate the expected monetary value (EMV) to make the necessary recommendations to the organization计算预期货币价值(EMV)以向组织提出必要的建议

参考答案:B、C(仅供参考)