The project management plan defines how the project is executed , monitored and controlled , and closed . it is progressively elaborated by updates ,and controlled and approved through the perform integrated __process.
A.Cost control
B.Schedule control
C.Change control
D.Risk control
参考答案:C(仅供参考) 收藏