Project work packages are typically decomposed into smaller componentscalled activities to provide a basis for (  ), scheduling, executing, and monitoring and controlling the project work.
A. reviewing
B. estimating
C. auditing
D. expecting

参考答案:B(仅供参考) 收藏

【解析】

普通会员无法查看试题解析。[开通试题解析服务]