Estimate Activity Durations is the process of estimating the number of work periods to complete indivities with estimated resources . The tools and technques is not including().
A、expert judgment
B、analogous estimating
C、requirements traceability matrix
D、three-point estimating
参考答案:C(仅供参考) 收藏