() includes the processes required to ensure that the project includes all the work required , and only the work required , to compete the project successfully . Managing the project scope is primarily concerned with defining and controlling what is not included in the project.
A、Create scope
B、Project stakeholder management
C、Preject scope management
D、Project cost management
参考答案:C(仅供参考) 收藏

【解析】