The communication management plan determines the information and communications needs of the stakeholders. In the following statements related to communication management plan.  (     ) is false.
A. The communication management plan is contained in or is a subsidiary plan of, the project management plan.
B. The  communication  management  plan  can  be  formal  or informal, highly detailed or broadly framed, and based on the needs of the project.
C. The  communication  manamgement  plan  organize  and summarize the information gathered,and present the results of any analysis as comparedthe performance measurement baseline.
D. The communication management plan can include guidelines project status meetings,project team meetings,e-meetines,and e-mail

参考答案:C(仅供参考) 收藏