The receiving  activities conduct analyses of the requirements with the requirements provider to ensure that a compatible, shared understandin  is reached on the meaning of the requirements. The result of this analysis and dialog is an ( )set of requirements.
A. agreed-to
B. agree-to
C. agree-to-do
D. agree-with

参考答案:A(仅供参考) 收藏

【解析】

普通会员无法查看试题解析。[开通试题解析服务]