信管网试题内容
信管网 导航

试题内容

On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and  (  )  are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
A.time estimating
B.cost estimating
C.project planning
D.schedule development

参考答案:D(仅供参考) 收藏

【解析】

普通会员无法查看试题解析。[开通试题解析服务]