You have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope. (  ) document provides this information.
A、Resource assignment matrix          
B、Change control plan
C、Project charter                           
D、Client organization chart

参考答案:B(仅供参考) 收藏