The following diagram denotes dependency between two activities A and B,It says()

A、B  can’t  start  before  A  is  finished
B、B  can’t  finish  before  A  is  finished
C、B  can’t  start  before  A  starts
D、B  can’t  finish  before  A   starts

参考答案:A(仅供参考) 收藏