Many useful tools techniques are used in developing schedule. ()s a schedule network analysis technique that modifies the project schedule to account for limited resource.
A. PERT
B. Resource levelling
C. Schedule compression
D. Critical chain method
参考答案:B(仅供参考) 收藏