With a clear SOW a contractor completes work as specified,but the buyer not pleased with the result.The contract is considered to be()。
A、incomplete because the buyer is not pleased
B、incomplete because the specs are incorrect
C、complete because the contractor is satisfied
D、complete because the contractor meets the terms and conditions of the contract
参考答案:D(仅供参考) 收藏