When required, the Perform Integrated Change Control Process includes a( ), which is a formally chartered group responsible for reviewing, evaluating, approving, deferring or rejecting changes to the project and for recording and communicating such decisions.
A.BBC
B.CCB
C.BCB
D.CBC

参考答案:B(仅供参考) 收藏