A critical path for a project is the series of activities that determine( )by which theprojectcan be completed
A.the earliest time
B.the latest time
C.the total time
D.the free time
参考答案:A(仅供参考) 收藏

【解析】

普通会员无法查看试题解析。[开通试题解析服务]