信管网综合知识

导航

2020年信息系统项目管理师上午综合知识真题与答案解析(70-75)

2020年11月10日来源:信管网 作者:cnitpm

2020年信息系统项目管理师上午综合知识真题与答案解析(70-75)

70、()can be scripted as a new science and technology,which is used to simulate human intelligence namely, computers simulate the way of human’s thinking and intelligent behavior, such as learning, reasoning thinking, planning,and so on 。
A.internet of things
B.cloud computing
C.artificial intelligence
D.big data
信管网参考答案:C
查看解析:www.cnitpm.com/st/432248048.html
71、()is preservation of confidentiality, integrity and availability of
information,in addition, other properties such as authenticity, accountability, non-repudiation and reliability can also be involved。
A、 Equipment security
B.、Network security
C.、Information security
D、Content security
信管网参考答案:C
查看解析:www.cnitpm.com/st/4322516727.html
72、() involres  choosing part of a population of interest for inspection
A、 Check list
B、 Check sheet
C、Statistical sampling
D、Questionnaire
信管网参考答案:C
查看解析:www.cnitpm.com/st/4322625747.html
73、()is the process of formalizing acceptance of the completed project
deliverables. The key benefit of this process is that it brings objectivity to
the acceptance process and increases the probability of final product, service,
or result acceptance by validating each deliverable。
A、 Validata scope
B、Define scope
C、Control scope
D、Collect requirement
信管网参考答案:A
查看解析:www.cnitpm.com/st/4322710877.html

温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!

分享至:
请使用浏览器的分享功能,把好文章分享给更多的人

信管网 - 信息系统项目管理专业网站

下载APP-在线学习

培训课程

0元畅享

考试题库

免费资料

APP下载