70、()can be scripted as a new science and technology,which is used to simulate human intelligence namely, computers simulate the way of human’s thinking and intelligent behavior, such as learning, reasoning thinking, planning,and so on 。
A.internet of things
B.cloud computing
C.artificial intelligence
D.big data
信管网参考答案:C
查看解析:www.cnitpm.com/st/432248048.html
71、()is preservation of confidentiality, integrity and availability of
information,in addition, other properties such as authenticity, accountability, non-repudiation and reliability can also be involved。
A、 Equipment security
B.、Network security
C.、Information security
D、Content security
信管网参考答案:C
查看解析:www.cnitpm.com/st/4322516727.html
72、() involres choosing part of a population of interest for inspection
A、 Check list
B、 Check sheet
C、Statistical sampling
D、Questionnaire
信管网参考答案:C
查看解析:www.cnitpm.com/st/4322625747.html
73、()is the process of formalizing acceptance of the completed project
deliverables. The key benefit of this process is that it brings objectivity to
the acceptance process and increases the probability of final product, service,
or result acceptance by validating each deliverable。
A、 Validata scope
B、Define scope
C、Control scope
D、Collect requirement
信管网参考答案:A
查看解析:www.cnitpm.com/st/4322710877.html