In an implementation project, the development phase has been outsourced to an off-shore team. During the execution of the project, the off-shore team states that vital information to proceed in the development is missing. However, the on-shore design team has stated that all design documents have been provided.What could most likely be the cause of this situation?
A、The communications management plan has not been created properly
B、The two teams do not get along well with each other
C、Project managers lack communication skills
D、The risk management plan has not been created properly