A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should( ).
A、assign change tasks to project members
B、call a meeting of the configuration control board
C、change the scope baseline
D、postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!
相关推荐