The project manager is completing the project the final product is finished, all defects found to date are corrected and the product is delivered to the client. The project manager announces the end of project. A week later the client contacts the project manager because they found a defect and they want to project manager to repair it. The client claims that the project is not yet closed because they are still testing the product. How does the project manager respond to this situation?
A、Tell the client that the project is finished and there will be no repairs to the defect because warranty period was not defined in the contract.
B、correct the defect and tell the client it’s the final repair to defects
C、correct the defect and get formal accept from client
D、Ask the client to send a change request to change the project scope statement

试题出处:http://www.ruantiku.com/shiti/3512813612.html
在下面提交答题后即可查看答案与考友试题分析

温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!

分享至:
请使用浏览器的分享功能,把好文章分享给更多的人

信管网 - 信息系统项目管理专业网站

下载APP-在线学习

培训课程

0元畅享

考试题库

免费资料

APP下载