信息系统项目管理师每日一练试题内容(2019/12/31)
试题1: ( )属于项目财务绩效评估的基本方法。
A.动态分析法
B.预期效益分析法
C.风险调整贴现率法
D.因果图
The parties to government procurement refer to the principal entities of all kinds that enjoy rights and undertake obligations in government procurement, including the procuring entities,the ( ) and the procuring agencies.
A、users
B、servers
C、producers
D、suppliers
下列关于项目型组织优缺点的描述中,不正确的是( )。
A.项目型组织结构单一,责权分明,利于统一指挥
B.项目型组织管理成本较低,项目环境利于沟通和知识共享
C.项目型组织沟通简洁、方便,目标明确单一,决策快
D.项目型组织的员工缺乏事业上的连续性和保障
A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should( ).
A.assign change tasks to project members
B.call a meeting of the configuration control board
C.change the scope baseline
D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
( )是正式批准一个项目的文档,或者是批准现行项目是否进入下一阶段的文档。
A.项目章程
B.项目合同
C.项目启动文档
D.项目工作说明书
从软件开发生命周期的角度划分,可将项目文档分为开发文档、产品文档和()
A、记录文档
B、测试文档
C、维护文档
D、管理文档
关于项目沟通技巧的叙述中。()是不正确的。
A、了解项目干系人不同的沟通风格,尽量采用对方能接受的沟通风格
B、正式和非正式的沟通相结合有利于关系的融洽
C、有效利用沟通的升级原则,先和对方沟通,然后和对方的上级沟通
D、尽量多地使用行话可以提高沟通效率
项目选择和项目优先级排序是项目组合管理的重要内容,其中()不属于结构化的项目选择和优先级排序的方法
A、DIPP分析
B、期望货币值
C、财务分析
D、决策表技术
The (1) process differs from the (2) process in that the former is primarily concerned with acceptance of the deliverables,while the latter is primarily concerned with correctness of the deliverables.
(1)A. Perform Quality Assurance
B. Validate Scope
C. Control Quality
D. Define Scope
(2)A. Perform Quality Assurance
B. Validate Scope
C. Control Quality
D. Define Scope