信管网章节习题

导航

未指定试题:aprojecthealthcheckidentifiedariskthatyo

2019年10月31日

试题来源:信管网 作者:cnitpm

试题分类:未指定

A project health check identified a risk that your project would not be completed on time. Several projects are competing for the same resources, and a serious resource conflict is emerging. As a result, you are quantifying the project’s risk exposure and determining what cost and schedule contingency reserves might be needed. You performed a schedule risk analysis using Monte Carlo analysis. The basis for your schedule risk analysis is the:
A、WBS
B、Gantt chart
C、Schedule network diagram and duration estimates
D、Probability/impact risk rating matrix

试题出处:http://www.ruantiku.com/shiti/3548111893.html
在下面提交答题后即可查看答案与考友试题分析

温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!

分享至:

信管网 - 信息系统项目管理专业网站

下载APP-在线学习