信息系统项目管理师每日一练试题内容(2019/10/25)
试题1: The project maintains a current and approved set of requirements over the life of the project by doing the following:
• ( )all changes to the requirements
• Maintaining the relationships among the requirements, the project plans, and the work products
• ……
A. Monitoring
B. Managing
C. Gathering
D. Reducing
The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project ’ s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that ( ).
A.the project is ahead of its planned schedule
B.less work was completed than was planned
C.the cost overrun for work completed
D.the cost under-run of performance to date
( )不是系统集成项目的直接成本。
A.进口设备报关费
B.第三方测试费用
C.差旅费
D.员工福利
Schedule development can require the review and revision of duration estimates and resource estimates to create an approved( )that can serve as a baseline to track progress.
A.scope statement
B.activity list
C.project charter
D.project schedule
E-MAIL 客户端程序要找到邮件服务器,FTP客户端程序要找到FTP服务器,WEB浏览器要找到WEB服务器,通常要用到( )
A、FTP服务器
B、DNS服务器
C、E-MAIL服务器
D、TELNET服务器
信息时代,除了传统的电子邮件、远程登录、新闻与公告等应用外,新型的Internet应用有基于WEB的网络应用和基于P2P的网络应用。( )是属于基于P2P的网络应用.
A、google
B、blog
C、网络共享课程
D、QQ
some team leaders think that the only way to ()their team is through cash incentives. However research proves that money is the last thing you would want to use
A、arouse
B、encourage
C、incite
D、motivate
在评标过程中,发现有一投标单位提交了两份不同的投标文件,而且招标文件中也未要求提交备选投标,则应()
A、否决其投标
B、以最低报价投标文件为准
C、以最高得分投标文件为准
D、征求投标法的建议后决定