PMO is established in a company to coordinate and manage numerous projects.PMO of the company proposed a specific organizational structure for project proposals, and took it as a standard in the implementation of the company. The characteristic of the organizational structure is set up to enjoy moderate to high authority, including full-time project managers with considerable authority and full-time project manage staff who can also control the project budget. What kind of the organizational structure should the PMO put forward ?
A、Strong matrix.
B、 Weak Matrix.
C、 Projectized.
D、 Functional.