信管网章节习题

导航

未指定试题:tomeettheschedule,adecisionwasmadetoouts

2019年01月31日

试题来源:信管网 作者:cnitpm

试题分类:未指定

To meet the schedule,a decision was made to outsource part of a project to an external manufacture. What steps should a project manager follow to assess potential suppliers before awarding a contract?
A、Bidder conferences,independent estimate,and procurement negotiations
B、Quantitative analysis,bidder conferences,and critical path analysis
C、Procurement negotiations,independent estimate,and performance report
D、Procurement performance review,expert judgment and proposal evaluation technique

试题出处:http://www.ruantiku.com/shiti/353523515.html
在下面提交答题后即可查看答案与考友试题分析

温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!

分享至:

信管网 - 信息系统项目管理专业网站

下载APP-在线学习