During the first year, a project experiences a significant amount of issues. At beginning of the second year, the project stabilizes, diminishing dramatically the number of issues. What should the project manager do ?
A、Cancel the remaining scheduled risk assessment sessions.
B、Diminish the amount of management reserve.
C、Continue identifying new risks and reassessing existing risks.
D、Perform a qualitative risk analysis of the residual risks.