The delivery of an inventory management system is being subcontracted based on the value of US$4,000,000. During deployment of the system, it cannot meet the quality requirements. The test needs extra time and money to be done. Which of the following process could contain additional testing and evaluation to provide US$20,000 ?
A、Risk Management Plan
B、Resource Management Plan
C、Change Management Plan
D、Quality management plan