信管网章节习题

导航

未指定试题:acontractedfirmisnotmeetingqualitystANDa

2018年09月03日

试题来源:信管网 作者:cnitpm

试题分类:未指定

A contracted firm is not meeting quality standards and the deliverables are frequently late. The project manager discovers there are no existing contract terms that could ensure a better. What should have been done by the project manager to prevent the seller’s low performance?
A、Have the project manager’s team do an impact analysis
B、Conduct procurement performance reviews
C、Conduct a risk reassessment
D、Be involved during the contract elaboration

试题出处:http://www.ruantiku.com/shiti/3502621596.html
在下面提交答题后即可查看答案与考友试题分析

温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!

分享至:

信管网 - 信息系统项目管理专业网站

下载APP-在线学习