A portion of a project’s work will be procured from an external source. The project team creates statement for the procurement plan and issues a request for proposal to multiple suppliers. Project team questions about the work from the prospective suppliers. What should the project team do to provide responses to prospective suppliers ?
A、Send out individual responses to each supplier.
B、Designate a single point of contact for each suppliers from the project team to handle questions.
C、Revise the request for proposal to include responses to all questions and circulate to all suppliers.
D、Hold bidder conferences to clarity all questions across all suppliers.