未指定试题:afterconductingamake-or-buyanalysisANDre

2018年07月02日

试题来源:信管网 作者:cnitpm

试题分类:未指定

After conducting a make-or-buy analysis and reviewing its results, your company decided to award a contract for project management services on a pharmaceutical research project. Because your company is new to project management and does not understand the full scope of services that may be needed under the contact, it is most appropriate to award a
A、Firm Fixed price contracts
B、Fixed price incentive Fee contracts
C、Cost plus fixed Fee contracts
D、Time-and-materials contract

试题出处:http://www.ruantiku.com/shiti/35359469.html
在下面提交答题后即可查看答案与考友试题分析

温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!