信管网章节习题

导航

未指定试题:aftertheworkbreakdownstructureiscrested,

2018年06月29日

试题来源:信管网 作者:cnitpm

试题分类:未指定

After the work breakdown structure is crested, the project manager starts the Identify Risks Process using the brainstorming technique. During this process, some potential risks are raised. What should the project manager do?
A、Change the project scope to avoid the risks.
B、Accept the risks and include their expected value to the project budget.
C、Define potential responses.
D、Implement workarounds to avoid the risks.

试题出处:http://www.ruantiku.com/shiti/3549812635.html
在下面提交答题后即可查看答案与考友试题分析

温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!

分享至:

信管网 - 信息系统项目管理专业网站

下载APP-在线学习