After the work breakdown structure is crested, the project manager starts the Identify Risks Process using the brainstorming technique. During this process, some potential risks are raised. What should the project manager do?
A、Change the project scope to avoid the risks.
B、Accept the risks and include their expected value to the project budget.
C、Define potential responses.
D、Implement workarounds to avoid the risks.