试题分类:英语 On some projects,especially ones of smaller scope,activity sequencing, activity resource estimating, activity duration estimating, and () are so linked that they are viewed as a single process that can be performed by a person over a relatively short period of time. A、time estimating B、cost estimating C、project planning D、schedule development 试题出处:http://www.ruantiku.com/shiti/3224526247.html 在下面提交答题后即可查看答案与考友试题分析 信管网参考答案:D 信管网解析:进入软题库查看解析 查看更多英语试题>>