2018年上半年系统规划与管理师上午综合知识真题试题与答案:
73、Change management would typically be composed of the raising and recording of changes, assessing the impact, cost, benefit and risk of proposed changes,developing business justification and obtaining approval, managing and coording change implementation, monitoring and reporting on implementation, reviewing and closing ().
A、change reason
B、change model
C、remediation plan
D、change requests
信管网参考答案:D