信管网试题分类练习

导航

英语试题:diagram1showsthesequenceofactivitiesforp

2018年05月16日

试题来源:信管网 作者:cnitpm

试题分类:英语

Diagram 1 shows the sequence of activities for project XYZ and its duration. The project manager is asked to reduce the project duration by two weeks. None of the activities can be fast tracked. Activities A and F cannot be crashed, activity G can be crashed by two weeks; and all other activities can be crashed by one week. To meet the new project duration requirement, which of the following will the project manager decide to do?

A. Crash activity G.
B. Crash activity C and D.
C. Crash activity G, C and D.
D. Crash activity G,F and C.

试题出处:http://www.ruantiku.com/shiti/3382628920.html
在下面提交答题后即可查看答案与考友试题分析

温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!

分享至:
请使用浏览器的分享功能,把好文章分享给更多的人

信管网 - 信息系统项目管理专业网站

下载APP-在线学习

培训课程

0元畅享

考试题库

免费资料

APP下载