During project execution, the customer wants to make a change in the project scope. What should the project manager do?
A、Ask for a change request
B、Advise the customer that there is no possibility for changes while the project is underway.
C、Rewrite the project plan with the new requirements and implement it.
D、Involve top management to plan a new budget and resources.