How should lessons learned from a previous project affect a current scope statement?
A、Science the work breakdown structure is complete,lessons learned will have no impact on the scope statement
B、The scope statement will develop more quickly than when the lessons learned are ignored
C、The past mistakes or errors of omission are less likely to be repeated in the current scope statement.
D、The scope statement will be unaffected by the lessons learned knowledge base, because all projects are unique.