In the completion of the project, the project manager archives the project plan, meeting minutes, regulatory reports, and other project documents. After completing these final project reports, what should the project manager do next?
A、 Distribute the final report to the sponsor.
B、 Close procurements.
C、 Obtain acceptance of project deliverables.
D、 Update the issue log.