Project manager according to the agreed project scope required the ability to determine the project team member candidates. What should the project manager do?
A、Negotiate with the functional manager to distribute the resource of project.
B、 Negotiate with the identified resources to join the project.
C、 Escalate the resource needs to the project sponsor immediately.
D、 Update the risk management log with the need for company.