信管网章节习题

导航

英语试题:aprojectmanagerleadsaprojecttobuildadata

2018年03月08日

试题来源:信管网 作者:cnitpm

试题分类:英语

A project manager leads a project to build a data center. The client submits a dramatic change to the project manager. Insisting that modification must be introduced as soon as possible involves incremental changes to the budget and an expectation of the overall schedule. What should the project manager do next ?
A、Advise the client to initiate the change as another project.
B、Present the client’s request at the next change control board meeting.
C、Include the client’s change and re-baseline the budget and schedule.
D、Ignore the request as the baseline for the budget and schedule have been agreed to.

试题出处:http://www.ruantiku.com/shiti/3383826464.html
在下面提交答题后即可查看答案与考友试题分析

温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!

分享至:

信管网 - 信息系统项目管理专业网站

下载APP-在线学习