The project manager is informed by the company’s internal auditor that the project documentations must be reviewed at the next quality audit. What is the purpose of this audit?
A、 Verify that the production quality meets customer expectations.
B、 Ensure the company’s processes align with ISO 9001.
C、 Check that the company’s quality process is followeD.
D、 Meet process improvement recommendations.