The project manager is responsible for a system integration project. Which documents are required to perform quality assurance on the project ?
A、Quality metrics, work performance information, project management plan.
B、 Project management plan, lessons learned, scope statement.
C、 Cost performance baseline, project management plan, schedule performance index.
D、 Project management plan, variance analysis, risk register.