During project execution, an important stakeholder, who is a capital investor in the client’s business, disagrees with a significant scope item. What should the project manager do ?
A、Advise the stakeholder that it is too late to change the scope
B、Agree to the scope change with the stakeholder
C、Apply the changes management plan for the stakeholder’s scope
D、Terminate the project because the scope is not aligned with the client’s business