信管网章节习题

导航

未指定试题:anorganizationreceivesproposalsfromfivep

2018年01月16日

试题来源:信管网 作者:cnitpm

试题分类:未指定

An organization receives proposals from five pre-qualified sellers for provision of services for a project. Selection of a seller will be based upon evaluation of several qualitative criteria. It is now required to shortlist two sellers based upon the proposals submitted. What tool or technique should the project manager use to establish the shortlist?
A、Seller rating system
B、Weighting system
C、Contract negotiation
D、Independent estimates

试题出处:http://www.ruantiku.com/shiti/3517120868.html
在下面提交答题后即可查看答案与考友试题分析

温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!

分享至:

信管网 - 信息系统项目管理专业网站

下载APP-在线学习