信管网试题分类练习

导航

英语试题:theprojectistheMIDdleofalong-termproject

2018年01月15日

试题来源:信管网 作者:cnitpm

试题分类:英语

The project is the middle of a long-term project when a major error is discovered by the develop team. This error can be fixed by implementing a large change to the scope of the project. This change could influence both time and budget plans. What should the project manager do first?
A、Analyze the change request and present it to the change control board.
B、 Implement the change request and inform the stakeholders afterwards.
C、 Implement the change request and present it to the change control board afterwards.
D、 Analyze the change request and present it to the steering committee.

试题出处:http://www.ruantiku.com/shiti/338089041.html
在下面提交答题后即可查看答案与考友试题分析

温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!

分享至:
请使用浏览器的分享功能,把好文章分享给更多的人

信管网 - 信息系统项目管理专业网站

下载APP-在线学习

培训课程

0元畅享

考试题库

免费资料

APP下载