信管网章节习题

导航

英语试题:theprojectbudgetisprovingtobeinaccurate.

2017年12月25日

试题来源:信管网 作者:cnitpm

试题分类:英语

The project budget is proving to be inaccurate. The SPI is 1.1, the team has had negative deviation from the activity attributes, and the sponsor has inserted herself on the change control board. What is the best thing for the project manager to do ?
A、Try to encourage the sponsor to remove herself from the change control boad.
B、 Re-compute the project schedule.
C、 Re-estimate the activity attributes.
D、 Calculate the cost performance index.

试题出处:http://www.ruantiku.com/shiti/3379411927.html
在下面提交答题后即可查看答案与考友试题分析

温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!

分享至:

信管网 - 信息系统项目管理专业网站

下载APP-在线学习