信管网章节习题

导航

英语试题:you’vebeenassignedtotakeovermanagingapro

2017年12月22日

试题来源:信管网 作者:cnitpm

试题分类:英语

You’ve been assigned to take over managing a project that should be half complete according  to the schedule. After an extensive evaluation, you discover that the project is running far behind schedule, and that the project will probably take twice the time originally estimated by the previous project manager. However, the sponsor has been told that the project is on schedule. What is the BEST course of action?
A、Try to restructure the schedule to meet the project deadline .
B、Report your assessment to the sponsor.
C、Turn the project back to the previous project manager.
D、Move forward with the schedule as planned by the previous project manager and report at the first missed milestone.

试题出处:http://www.ruantiku.com/shiti/3377125448.html
在下面提交答题后即可查看答案与考友试题分析

温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!

分享至:

信管网 - 信息系统项目管理专业网站

下载APP-在线学习