信管网章节习题

导航

英语试题:fourmonthsintoa10-monthproject,theprojec

2017年12月12日

试题来源:信管网 作者:cnitpm

试题分类:英语

Four months into a 10-month project, the project manager realizes that the project is behind schedule and slippage will lead to an overrun of 25% of the project’s budget. A change request is created, but when the project manager seeks approval, the executive is reluctant to do so. What could be the reason for this executive’s reluctance ?
A、Lack of the project management plan approval.
B、 Lack of the risk management plan approval.
C、 Lack of the communications management plan approval.
D、 Lack of the change management plan approval.

试题出处:http://www.ruantiku.com/shiti/3373810380.html
在下面提交答题后即可查看答案与考友试题分析

温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!

分享至:

信管网 - 信息系统项目管理专业网站

下载APP-在线学习