To generate creative ideas during the Collect Requirements Process, the project manager solicits a group of experts through a series of questionnaires, which are kept anonymous and whose answers are went directly back to the project manager. This technique is known as which of the following?
A、Nominal group technique
B、Delphi technique
C、Brainstorming
D、Mind mapping