The company’s accounting system project is close to the end of its execution phase when the finance director discovers an important requirement is missing, and instructs the project manager to immediately implement the change. If the project deliverable is produced according to the current specification, it will not be usable. The change is significant, but the project manager could possibly meet the project deadline, if the work is started immediately. What should the project manager do first?
A、Call the project sponsor and ask if the finance director is authorized to order changes to the project scope.
B、Explain to the finance manager that the change may delay the project beyond the deadline.
C、Start processing the request according to the project’s change management plan
D、Estimate, plan, and implement the change in order to not lose time during the change request process.

试题出处:http://www.ruantiku.com/shiti/337697287.html
在下面提交答题后即可查看答案与考友试题分析

温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!

分享至:
请使用浏览器的分享功能,把好文章分享给更多的人

信管网 - 信息系统项目管理专业网站

下载APP-在线学习

培训课程

0元畅享

考试题库

免费资料

APP下载