A project manager discovers that a technical lead approved a more expensive solution than what was budget. The technical insists it was necessary to meet the project deliverables. To avoid this in the future what should the project manager do ?
A、Create a communications plan.
B、 List this incident a risk.
C、 Control the project manage plan.
D、 Create a change manage plan.